Explosives Store Update 29 October 2014

Work continued on the back inner wall and one of the side walls.  Sourcing the correct stones is becoming more difficult.  We have cut and dressed some stones to get a better fit in the wall. Mortar is now slower to dry but the weather continues to be relatively mild.

We are planning to complete the inner walls and install the main roof timber on Sunday 2nd November. The weather forecast is good and should enable us to complete the walls.

The timber for the door frame is on order, together with the roof timbers. Once delivered, we will be very dependent upon the weather. Completion may not be possible until early in 2015.

Colin Fowler, Alec Langley, Graham Brooks and Joyce Jackson were working on site today.