NMCS Work Programme 2015 Version 1 dated 22 03 2015
Small Jobs
Assay House door seals – install
Hodgson’s shop window – repair broken pane
Replace putty on various windows and repaint
Repaint Assay House upstairs door
Paint Assay house interior
Medium Jobs
Dismantle panels in Barracks ground floor and tidy up room
Move Eimco to better position in Barracks
Moving deck winch under cover in Barracks
Pointing – assorted places with lime mortar
Barracks floor – replace floorboards near entrance
Assay House South doorframe – replace lower sections
Hodgson’s High Level shop – fix chimney lead flashing
Large Jobs
River wall below Smallcleugh I complete emergency repairs
Barracks North Door & Frame – strengthen rotting door and frame
Flagstones outside Barracks South door – lay flagstones when SMC confirmed
Ongoing Jobs
Pothole filling – access track
Weeding – particularly smelting mill area, and remove thistles anywhere
Litter picking
Projects
North Explosives Store: install roof timbers and roof, construct two doors and frames, install floor and interior walls, complete wall reconstruction
Restore Eimco
Restore deck winch