JUNE 2017 UPDATE – MINE WATER TREATMENT SCHEMES

This is a copy of as recent letter from the Environment Agency and the Coal Authority.

Community up- date June 2017

1 Next public participation meetings

A short list of areas for the proposed mine water treatment schemes for the Nent Haggs adit in Nentsberry and the Caplecleugh adit in Nenthead has now been created.
This follows discussions regarding the long list of proposed areas undertaken at the public meetings in October 2016.

The next public participation events will be on 6 and 7 July 2017 at Nenthead Village Hall.

On this occasion we will be available for an extended time period from 8.00am to 9.00pm on each day, at a drop in event. We hope that this will allow more people the opportunity to see the proposals and talk to the team.

Each short listed site will be displayed with a site design, photograph, ordnance survey location map and information relating to the site criteria.

As usual there will be representatives from both the Coal Authority and the Environment Agency on hand to answer questions relating to the short list of sites.

2 Update on sediment trap (check weir) installation at Nentsberry and dredging works at Nenthead

A planning application for the work to install a sediment trap in the river, with vehicle access across the field near the Old Chapel, was submitted to Eden District Council on 15 May 2017.
Full details are available on their website at: www.eden.gov.uk  – go to ‘search planning applications’ and use application number: 17/0362
This information has been circulated locally by email and properties nearby to the proposed site have been informed through the planning process.

Construction works at Nentsberry are due to commence during mid July, subject to the necessary statutory approvals. These works are scheduled for 12 to 15 weeks with completion due before the end of October 2017. The site team will endeavour to minimise any disruption.

It is necessary to carry out access improvement works and this will be managed by 2-way traffic lights. The duration of these works will be carried out earlier in the project to minimise traffic disruption.
Works at Nenthead to dredge the existing check weirs is due to commence in July, subject to the necessary statutory approvals. These are due to be completed in 6 to 8 weeks.
During the works it will be necessary to segregate the public from the operational plant for health and safety reasons, especially to minimise the disruption to walkers. Access to private properties will be maintained at all times.

Should you have any concerns or questions regarding either project, please do contact the Coal Authority on the Nent Haggs number 0345 762 6848 or contact me directly in office hours on the number below.

3 Other work and surveys

United Utilities are have almost finished their work to the mains water supply at Nentsberry. There will be some presence on site to test the new system which should be completed during w/c 12 June.
Survey works on the long list areas for mine water treatment schemes will continue throughout June, leading up to the next meetings.
There are specific ground investigations for the check weir build project planned for w/c 19 June.

Previous information relating to these projects can be found at:

https://www.gov.uk/government/collections/nent-haggs-mine-water-treatment-scheme-proposed

If you have any questions, please don’t hesitate to contact me – Jeremy Regan

T: 01623 637178

E: jeremyregan@coal.gov.uk,  Stakeholder Engagement Manager, The Coal Authority